0
Fixed

When entering 50/90 estimates the error message that appears when the 90 value is less than the 50 value is incorrect - it says the 90 value MUST be less than the 50 value when in fact the reverse is true.

Carl C 10 years ago updated by Matthew O'Riordan (Founder) 10 years ago 0

When I accidentally entered a value of 1 for the 90 estimate after entering 5 for the 50 estimate an error message appeared stating that the 90 value must be less than the 50 value. The wording of the message needs to be corrected to state that the 90 value must be greater than the 50 value.

Answer

Answer
Fixed

Hi 


This issue is now fixed.


Thanks for pointing this out.  If you come across any other issues please shout.


Matt

Started

Thanks for pointing this out, we will fix.

Answer
Fixed

Hi 


This issue is now fixed.


Thanks for pointing this out.  If you come across any other issues please shout.


Matt